EFFECT OF OWNER APPROVALS & ACQUIESENCE

If the Owner advertises a Pre-Bid Schedule or does not reject or raise timely objections to an "As-Planned" Schedule submitted by a contractor, it will be bound by the schedule and expected to meet its obligations thereunder.

  • Fullerton Construction Co., ASBCA 12275, 69-2 BCA 7,876
  • Frank Briscoe Co., Inc., GSBCA 3545, 73-1 BCA 9,890